Swanston Golf New Clubhouse
Latest news:
30th October 2007:
The electricity pole in front of the new clubhouse is being
removed and the cable put underground. This will give
an uninterrupted view of the new 18th green from the main
clubhouse bar/balcony. A new power transformer is
being installed on the next pole up the road to increase the
power supply to the new building and irrigation pumps.
5th October 2007:
We're nearly there. Building Control picked up that
the builders had not fitted 'panic bars' on all the exit
doors. These have now been ordered, but are taking 4
weeks to be delivered from America. As a result the
official opening has now been put back till early November.
12th July 2007:
Top floor offices are complete, bar/restaurant is only a few
weeks away from completion, changing rooms, toilets,
showers, pro-shop on the lower floor are all under
construction.

View of new building with new 6th green in
foreground.
The new 18th green for the main course, new short
course and driving range are visible to the left of
the new clubhouse building, with the city bypass and
Fairmilehead housing in the distance. |

'Before' / 'After' from road |

'Before' / 'After' from course |

Internal collage of bar looking out onto balcony
and 1st hole |
15th June 2007:
The latest estimate for completion of the new clubhouse
is early September.
Click on the graphic below to see the latest location
of golf lockers, changing rooms and starter/shop.
17th January 2007:
Gavin Jefcoate Architects have prepared some images to help
us all visualise the finished building. We expect the
stone to be more in keeping with the stone used in the
nearby farm buildings but apart from that these images are
pretty accurate.
18th October:
Steel frame has been delivered and erected, showing the
extent of the new building. Pre-cast concrete floors
arrive next week.

View of new building with new 6th green in
foreground |

'Before' / 'After' from road |

'Before' / 'After' from course |
30th June:
After a tender period a contract to supply and erect the
steel-frame that makes up the structural element of the
entire 3 storeys of the new building has been awarded to a
subcontractor.
25th May: The foundations of the new clubhouse
have been dug to their finished level.
3rd May: The old clubhouse has been demolished.

Before |

After |
14th April: New temporary facilities opened on 6th
April. Demolition of old building is underway.
The final structure is set to come down on 3rd May.
Main construction still set for July start.