Golf Home
  Contact Details
  Golfers News
  Visitor Information
  Course News
  Clubhouse News
  Bar/Restaurant News
  John Gallagher News
  Accommodation



 



Swanston Golf New Clubhouse

Latest news:

30th October 2007:
The electricity pole in front of the new clubhouse is being removed and the cable put underground.  This will give an uninterrupted view of the new 18th green from the main clubhouse bar/balcony.  A new power transformer is being installed on the next pole up the road to increase the power supply to the new building and irrigation pumps.

5th October 2007:
We're nearly there.  Building Control picked up that the builders had not fitted 'panic bars' on all the exit doors.  These have now been ordered, but are taking 4 weeks to be delivered from America.  As a result the official opening has now been put back till early November.

12th July 2007:
Top floor offices are complete, bar/restaurant is only a few weeks away from completion, changing rooms, toilets, showers, pro-shop on the lower floor are all under construction.


View of new building with new 6th green in foreground. 
The new 18th green for the main course, new short course and driving range are visible to the left of the new clubhouse building, with the city bypass and Fairmilehead housing in the distance.

'Before' / 'After' from road

'Before' / 'After' from course

Internal collage of bar looking out onto balcony and 1st hole

 

15th June 2007:
The latest estimate for completion of the new clubhouse is early September.
Click on the graphic below to see the latest location of  golf lockers, changing rooms and starter/shop.

Adobe Acrobat Version

17th January 2007:
Gavin Jefcoate Architects have prepared some images to help us all visualise the finished building.  We expect the stone to be more in keeping with the stone used in the nearby farm buildings but apart from that these images are pretty accurate.

18th October:
Steel frame has been delivered and erected, showing the extent of the new building.  Pre-cast concrete floors arrive next week.


View of new building with new 6th green in foreground

'Before' / 'After' from road

'Before' / 'After' from course

30th June:
After a tender period a contract to supply and erect the steel-frame that makes up the structural element of the entire 3 storeys of the new building has been awarded to a subcontractor.  

25th May: The foundations of the new clubhouse have been dug to their finished level.

 

3rd May: The old clubhouse has been demolished.


Before

After

14th April: New temporary facilities opened on 6th April.  Demolition of old building is underway.  The final structure is set to come down on 3rd May.  Main construction still set for July start.

New gravel surface
for carpark
Temporary clubhouse
from outside
Temporary clubhouse
inside

 

Current drawings:  
Ground floor plans First floor plans
Second floor plans West elevation
North elevation  

 


©2004 Swanston Farm Ltd.
Site design by Farmore